“MUHSIN RIZVIĆ” GYMNASIUM, KAKANJ
Šehida 32, Kakanj
Area: 2.240
Energy efficiency measures:
- Roof replacement
Contracted per object: 75.207,34 BAM
“MUHSIN RIZVIĆ” GYMNASIUM, KAKANJ
Šehida 32, Kakanj
Area: 2.240
Energy efficiency measures:
Contracted per object: 75.207,34 BAM
“RIZAH ODŽEČKIĆ” GYMNASIUM, ZAVIDOVIĆI
Stjepana Radića 43, Zavidovići
Area: 1.467 m2
Energy efficiency measures:
Contracted per object: 51.258,62 BAM.
PUBLIC INSTITUTION FACULTY OF PHILOSOPHY, UNIVERSITY OF ZENICA
Address: Zmaja od Bosne 56, Zenica
Heated area: 2,680 m2
Energy efficiency measures:
Total investments (BAM with VAT): 647,090.39
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 54,282.63
Total energy savings (thermal and electrical): 344,397 kWh/year
CO2 emissions: 124 tCO2 /year
Start of works: 08/10/2022
Works completed/Date of technical acceptance: 17/05/2022
PUBLIC INSTITUTION “FACULTY OF METALLURGY AND TECHNOLOGY, UNIVERSITY OF ZENICA”
Address: Travnička cesta, Zenica
Heated area: 5,819.49 m2
Energy efficiency measures:
Total investments (BAM with VAT): 1,228,476.44
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 101,730
Total energy savings (thermal and electrical): 639,213 kWh/year
CO2 emissions: 171 tCO2 /year
Start of works: 08/10/2022
Works completed/Date of technical acceptance: 17/05/2022
PUBLIC INSTITUTION FACULTY OF MECHANICAL ENGINEERING, UNIVERSITY OF ZENICA
Address: Fakultetska 3, Zenica
Heated area: 6,216.22 m2
Energy efficiency measures:
Total investments (BAM with VAT): 1,082,757.64
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 82,910
Total energy savings (thermal and electrical): 525,377 kWh/year
CO2 emissions: 277 tCO2 /year
Start of works: 08/10/2022
Works completed/Date of technical acceptance: 17/05/2022
ELEMENTARY SCHOOL “KULIN BAN” VISOKO
Address: Gornje Rosulje 1, Visoko
Heated area: 3,007.74 m2
Energy efficiency measures:
Total investments (BAM with VAT): 640,828.53
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 76,196.11
Total energy savings (thermal and electrical): 386,854 kWh/year
CO2 emissions: 185 tCO2 /year
Start of works: 5/10/2021
Works completed/Date of technical acceptance: 2/8/2022
PUBLIC INSTITUTION ELEMENTARY SCHOOL “SKENDER KULENOVIĆ”, ZENICA
Address: Radakovo, Zenica
Heated area: 3,460.62 m2
Energy efficiency measures:
Total investments (BAM with VAT): 462,843.05
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 55,525.24
Total energy savings (thermal and electrical): 307,851 kWh/year
CO2 emissions: 76 tCO2 /year
Start of works: 08/10/2022
Works completed/Date of technical acceptance: 17/05/2022
ELEMENTARY SCHOOL “MUSTAFA MULIĆ”, ŠIJE, MATUZIĆI
Address: Šije, Matuzići
Heated area: 950 m2
Energy efficiency measures:
Total investments (BAM with VAT): 349,401.50
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 13,443.80
Total energy savings (thermal and electrical): 168,049 kWh/year
CO2 emissions: 130 tCO2 /year
Start of works: 21/09/2021
Works completed/Date of technical acceptance: 20/04/2022
ELEMENTARY SCHOOL MAK DIZDAR ZENICA
Address: Ćurkovića put 17, Zenica
Heated area: 5,375 m2
Energy efficiency measures:
Total investments (BAM with VAT): 1,078.686.02
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 81,268.85
Total energy savings (thermal and electrical): 572.454 kWh/year
CO2 emissions: 300 tCO2 /year
Start of works: 08/10/2022
Works completed/Date of technical acceptance: 17/05/2022
ELEMENTARY SCHOOL MULA MUSTAFA BEŠESKIJA, VISOKO
Address: Donje Moštre, Visoko
Heated area: 2,378 m2
Energy efficiency measures:
Total investments (BAM with VAT): 449,503.81
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 25,886
Total energy savings (thermal and electrical): 442.562 kWh/year
CO2 emissions: 158 tCO2 /year
Start of works: 5/10/2021
Works completed/Date of technical acceptance: 2/8/2022