ENERGY EFFICIENCY MEDIA TRAINING IN KONJIC

Media representatives had the opportunity to learn of good practices in the field of energy efficiency from neighbouring countries.

IMG_0042

An interactive workshop with media representatives was organized in Konjic as a part of the World Bank project “Bosnia Energy Efficiency Project”, which is implemented by the Federal Ministry of Physical Planning. During the two-day informal gathering, media had the opportunity to participate in interactive lectures on the topic of energy efficiency. They also visited Konjic High School, where they could further learn how to implement energy efficiency measures through practical examples.

 

The media representatives were given a presentation of the project; attended interactive lectures that covered the theoretical aspect of energy efficiency; and were given presentation material that further explained how materials are used in the implementation of energy efficiency measures, as well as ways they can implement them. Media representatives had the opportunity to learn of good practices in the field of energy efficiency from neighbouring countries.

 

The guided tour through Konjic High School, where implementation of energy efficiency measures is currently in progress, was an additional opportunity for the media representatives to learn about how the implementation actually looks like at the construction site.

Education of media about energy efficiency held in Konjic

Grand Opening of the Surgical disciplines building in Tuzla

Grand Opening of the Department of Orthopedics and Traumatology, Sarajevo

Secondary School Čapljina

Secondary School Čapljina

Address: Ruđera Boškovića 9, Čapljina

Heated area: 4,770 m2


Energy efficiency measures:

  • Thermal insulation of the facade;
  • Reconstruction of the roof and thermal insulation of the ceiling;
  • Replacement of facade openings;
  • Installation of the new pellet boiler;
  • Installation of dynamic thermostatic radiator valves;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;

Total investments (BAM with VAT): 996,062.76 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM):  166,231
Total energy savings (thermal and electrical): 705,600.00 kWh/year
CO2 emissions: 62 tCO2 /year
Works completed: 12/2016

After Sarajevo, Hospital for Surgical Disciplines in Tuzla is Retrofitted

BEEP continues with its activities. Another clinical center was retrofitted according to international standards; this time, a clinic in Tuzla.

IMG_3746

 

As a part of  biggest energy efficiency project in Bosnia and Herzegovina World Bank “Bosnia energy efficiency project” (BEEP) , shortly after the opening of the Clinic of Orthopedics and Traumatology in Sarajevo, energy efficiency measures were being implemented on the selected object in Tuzla.

 

The Clinical Center in Tuzla, namely the surgical disciplines building, was retrofit according to the international standards and energy efficiency measures were implemented. Thermal insulation of facades was built in, with 10 cm of total thickness of facades on an area of more than 4,800 m2. A total of 607 worn out openings were also replaced with new openings that have a very low coefficient of heat. The implemented system also helps because it assures automatic temperature control.

 

“We are proud that today we have the honor to officially open the retrofitted surgical disciplines building in the Clinical Center in Tuzla. Just as a reminder, the World Bank project “Energy Efficiency in Bosnia” for the Federation of Bosnia and Herzegovina has started in December 2015., and here we are today ready to officially open the retrofitted building. This of course, would not be possible without the absolute support that we have received and the very good understanding between all parties involved in the project – representatives of beneficiaries, representatives of contractors and supervision, and also from the the project Steering Committee and whole team of PIU. The works, carried out by domestic companies, have been completed on time, and will help to achieve the project objectives, but also demonstrate the benefits of energy efficiency. As it is well known, Bosnia and Herzegovina has a fairly high level of energy inefficiency, but, on the other hand, significant potential in this field, as well,” said the head of the World Bank Project for the Federation of Bosnia and Herzegovina, Mustafa Čopelj.

 

According to the previous calculations, the expected savings on an annual basis are 126.000 BAM. Specific and accurate data on energy savings will be available in the coming winter season, considering that under this project permanent equipment for measurement of energy consumption was installed, also measuring the temperature and humidity.

 

As announced by the implementation unit, Psychiatric Hospital of the University Clinical Hospital Mostar will also open soon

Secondary School Konjic

SECONDARY SCHOOL KONJIC

Address: Maršala Tita 80, Konjic

Heated area: 5,115 m2

Energy efficiency measures:

 

  • Thermal insulation of the facade
  • Repairs and thermal insulation of passable and non-passable roofs
  • Replacement of facade openings
  • Installation of dynamic thermostatic radiator valves
  • Installation of the new pellet boiler
  • Installation of equipment for measuring energy consumption
  • Installation of temperature and humidity monitoring equipment

Total investments (BAM with VAT): 843,904.20 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 167,529 BAM
Total energy savings (thermal and electrical): 499.767,00 kWh/year
CO2 emissions: 233 tCO2 /year
Works completed: 1/2017

Public Institution Fourth Elementary School Mostar

PUBLIC INSTITUTION FOURTH ELEMENTARY SCHOOL MOSTAR

Address: Salke Šestića 23, Mostar

Area: 4,230 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade;
  • Rehabilitation and thermal insulation of flat and sloping roofs;
  • Replacement of facade openings;
  • Installation of the new pellet boiler;
  • Installation of dynamic thermostatic radiator valves;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;

Total investments (BAM with VAT): 761,531.60 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 99,757
Total energy savings (thermal and electrical): 323,097.00 kWh/year
CO2 emissions: 111 tCO2 /year
Works completed: 12/2016

Fra Didak Buntić Elementary School

FRA DIDAK BUNTIĆ ELEMENTARY SCHOOL

Address: Kralja Tomislava 94, Čitluk

Area: 3,255 m2


Energy efficiency measures:

 
  • Thermal insulation of the facade;
  • Thermal insulation of the ceiling of the building;
  • Replacement of facade openings;
  • Installation of the new pellet boiler;
  • Installation of dynamic thermostatic radiator valves;
  • Replacement of lighting fixtures with more energy efficient ones;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;


Total investments (BAM with VAT): 474,330.57 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 29,425
Total energy savings (thermal and electrical): 255.005,00 kWh/year
CO2 emissions: 96 tCO2 /year
Works completed: 12/2016

Health Centre Jablanica

Health Centre Jablanica

Address: Sulje Čilića 15, Jablanica

Heated area: 1,800 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade;
  • Thermal insulation of the attic space;
  • Replacement of facade openings;
  • Installation of dynamic thermostatic radiator valves Installation of the new pellet boiler;
  • Installation of equipment for measuring energy consumption;
  • Installation of equipment for monitoring temperature and humidity;

Total investments (BAM with VAT): 288,869.51 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 91,604 
Total energy savings (thermal and electrical): 293,313.00 kWh/year
CO2 emissions: 94 tCO2 /year
Works completed: 1/2017