Elementary school April 15, Kakanj

ELEMENTARY SCHOOL APRIL 15, KAKANJ

Address: 29. Novembar 35, Kakanj

Heated area: 2,120 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade;
  • Thermal insulation of the part of the attic space;
  • Replacement of facade openings;
  • Rehabilitation of the existing part of the cover – replacement of salonite panels with a steel sheet cover;
  • Installation of radiators in the hall;
  • Installation of dynamic thermostatic radiator valves;
  • Installation of equipment for measuring energy consumption and;
  • Installation of equipment for monitoring temperature and humidity;

Total investments (BAM with VAT): 298,414.64
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 34,211
Total energy savings (thermal and electrical): 280,237.00 kWh/year
CO2 emissions: 66 tCO2 /year
Works completed: 04/2018

Gymnasium Rizah Odžečkić

GYMNASIUM RIZAH ODŽEČKIĆ

Address: Stjepana Radića 43, Zavidovići

Heated area: 1,467 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade; 
  • Replacement of facade openings;
  • Thermal insulation of the ceiling towards the attic;
  • Partial replacement of lighting fixtures with more energy efficient ones;
  • Installation of motion and daylight sensors;
  • Installation of dynamic thermostatic radiator valves;
  • Replacement of energy source;
  • Installation of equipment for measuring energy consumption and monitoring temperature and humidity;
  • Installation of new pellet boilers;
  • Installation of equipment for measuring energy consumption and;
  • Installation of equipment for monitoring temperature and humidity;

Total investments (BAM with VAT): 327,266.31
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 42,099
Total energy savings (thermal and electrical): 128,098.00 kWh/year
CO2 emissions: 32 tCO2 /year
Works completed: 04/2018

Elementary school March 21

ELEMENTARY SCHOOL MARCH 21

Address: Trg 21. mart 12, Matuzići, Doboj Jug

Heated area: 1,953 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade;
  • Replacement of facade openings;
  • Thermal insulation of the ceiling towards the attic;
  • Repair of part of the roof;
  • Replacement of lighting fixtures with more energy efficient ones;
  • Installation of motion sensors;
  • Installation of dynamic thermostatic radiator valves;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;
  • Installation of the new pellet boiler;

Total investments (BAM with VAT): 141,182.75
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 14,307
Total energy savings (thermal and electrical):  135,151.00 kWh/year
CO2 emissions: 28 tCO2 /year
Works completed: 04/2018

Ivan Fra Frane Jukića Elementary School

IVAN FRA FRANE JUKIĆA ELEMENTARY SCHOOL

Address: Sivša bb, Usora

Heated area: 488 m2


Energy efficiency measures:

 
  • Thermal insulation of the facade;
  • Thermal insulation of the ceiling towards the attic;
  • Replacement of lighting fixtures with more energy efficient ones;
  • Installation of the new pellet boiler;
  • Installation of equipment for measuring energy consumption;
  • Installation of equipment for monitoring temperature and humidity;

Total investments (BAM with VAT): 86,483.84
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 4,899
Total energy savings (thermal and electrical): 14,517.00 kWh/year
CO2 emissions: 21 tCO2 /year
Works completed: 04/2018

Public Institution First Elementary School Zavidovići

PUBLIC INSTITUTION FIRST ELEMENTARY SCHOOL ZAVIDOVIĆI

Address: Safvet bega Bašagića 10, Zavidovići

Heated area: 2,620 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade and ceiling;
  • Replacement of facade openings;
  • Installation of dynamic thermostatic valves;
  • Replacement of lighting fixtures with more energy efficient ones;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;

Total investments (BAM with VAT): 362,783.27
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 11,693
Total energy savings (thermal and electrical): 299,767.00 kWh/year
CO2 emissions: 88 tCO2 /year
Works completed: 11/2016

Public Institution Elementary School Musa Cazim Catic

PUBLIC INSTITUTION ELEMENTARY SCHOOL MUSA CAZIM CATIC

Address: Školska 23, Zenica

Heated area: 3,423 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade;
  • Replacement of facade openings;
  • Installation of dynamic thermostatic radiator valves;
  • Improvement of the central heating system;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;

Total investments (BAM with VAT): 455,782.28
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 49,213
Total energy savings (thermal and electrical): 363,661.00 kWh/year
CO2 emissions: 100 tCO2 /year
Works completed: 11/2016

Public Institution Elementary School Hamdija Kresevljakovic, Kakanj

PUBLIC INSTITUTION ELEMENTARY SCHOOL HAMDIJA KRESEVLJAKOVIC, KAKANJ

Address: Šehida 2, Kakanj

Heated area: 3,120 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade and ceiling of the pitched roof;
  • Replacement of facade openings;
  • Improvement of the central heating system;
  • Installation of dynamic thermostatic radiator valves;
  • Partial replacement of lighting fixtures with more energy efficient ones;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment

Total investments (BAM with VAT): 332,627.59
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 49,894
Total energy savings (thermal and electrical): 368,745.00 kWh/year
CO2 emissions: 100 tCO2 /year
Works completed: 11/2016

Tešanj General Hospital

TEŠANJ GENERAL HOSPITAL

Address: Braće Pobrić, Tešanj

Heated area: 5,844 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade;
  • Replacement of facade openings;
  • Thermal insulation of the attic and roof;
  • Installation of new pellet boilers;
  • Reconstruction of the roof;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;

Total investments (BAM with VAT): 718,293.76
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 161,082
Total energy savings (thermal and electrical): 686,930.00 kWh/year
CO2 emissions: 130 tCO2 /year
Works completed: 11/2016

Combined Secondary School, Žepče

COMBINED SECONDARY SCHOOL, ZEPCE

Address: Zagrebačka 2, Žepče

Heated area: 1,860 m2


Energy efficiency measures:

 

  • Thermal insulation of facade and the ceiling of the sloping roof;
  • Partial replacement of facade openings;
  • Installation of dynamic thermostatic radiator valves;
  • Replacement of lighting fixtures with more energy efficient ones;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;
  • Improvement of the central heating system;

Total investments (BAM with VAT): 170,792.39
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 22,152
Total energy savings (thermal and electrical): 158,650.00 kWh/year
CO2 emissions: 28 tCO2 /year
Works completed: 11/2016