About project
ELEMENTARY SCHOOL MULA MUSTAFA BEŠESKIJA, VISOKO
Address: Donje Moštre, Visoko
Heated area: 2,378 m2
Energy efficiency measures:
- Thermal insulation of facade walls;
- Thermal insulation of the ceiling;
- Thermal insulation and replacement of the cover of the sports hall;
- Replacement of part of the existing joinery/metalwork;
- Partial replacement of lighting fixtures;
- Installation of dynamic thermostatic valves;
- Installation of equipment for measuring energy consumption;
- Installation of temperature and humidity monitoring equipment;
Total investments (BAM with VAT): 449,503.81
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 25,886
Total energy savings (thermal and electrical): 442.562 kWh/year
CO2 emissions: 158 tCO2 /year
Start of works: 5/10/2021
Works completed/Date of technical acceptance: 2/8/2022