Public Institution Elementary School Srednje

PUBLIC INSTITUTION ELEMENTARY SCHOOL SREDNJE

Address: Srednje bb, Ilijaš

Heated area: 2,346 m2


Energy efficiency measures:

 

  • Replacement of facade openings;
  • Thermal insulation of the facade;
  • Installation of dynamic thermostatic radiator valves;
  • Installation of the new pellet boiler;
  • Installation of additional heating elements/radiators;
  • Replacement of lighting fixtures with more energy efficient ones;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;
  • Replacement of energy source;

Total investments (BAM with VAT): 488,870.16 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 56,564
Total energy savings (thermal and electrical): 210,281.00  kWh/year
CO2 emissions: 86 tCO2 /year
Works completed: 11/2016

Public Institution Elementary School Hašim Spahić

PUBLIC INSTITUTION ELEMENTARY SCHOOL HAŠIM SPAHIĆ

Address: Krajiška bb, 71000 Sarajevo

Heated area: 2,539 m2


Energy efficiency measures:

 

  • Replacement of facade openings;
  • Thermal insulation of the facade;
  • Thermal insulation of the ceiling towards the attic and the roof of the sports hall Installation of dynamic thermostatic radiator valves;
  • Hydraulic balancing of the heating system;
  • Automatic regulation for the heating system;
  • Partial replacement of lighting fixtures with more energy efficient ones;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;

Total investments (BAM with VAT): 450,273.48 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 20,317
Total energy savings (thermal and electrical): 414,342.00 kWh/year
CO2 emissions: 91 tCO2 /year
Works completed: 11/2016

University Clinical Center Tuzla – Clinic for Surgical Branches Tuzla

UNIVERSITY CLINICAL CENTER TUZLA – CLINIC FOR SURGICAL BRANCHES TUZLA

Address: Rate Dugonjića bb, Tuzla

Heated area: 11,450 m2


Energy efficiency measures:

 
  • Thermal insulation of the facade
  • Replacement of external joinery
  • Regulation of the heating system by means of three-way valves
  • Installation of equipment for measuring energy consumption, as well as equipment for monitoring temperature and humidity

Total investments (BAM with VAT): 1,037,923.25
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 126,861
Total energy savings (thermal and electrical): 1,822.604.00 kWh/year
CO2 emissions: 285 tCO2 /year
Works completed: 06/2016

Public Institution First Elementary School Zavidovići

PUBLIC INSTITUTION FIRST ELEMENTARY SCHOOL ZAVIDOVIĆI

Address: Safvet bega Bašagića 10, Zavidovići

Heated area: 2,620 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade and ceiling;
  • Replacement of facade openings;
  • Installation of dynamic thermostatic valves;
  • Replacement of lighting fixtures with more energy efficient ones;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;

Total investments (BAM with VAT): 362,783.27
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 11,693
Total energy savings (thermal and electrical): 299,767.00 kWh/year
CO2 emissions: 88 tCO2 /year
Works completed: 11/2016

Public Institution Elementary School Musa Cazim Catic

PUBLIC INSTITUTION ELEMENTARY SCHOOL MUSA CAZIM CATIC

Address: Školska 23, Zenica

Heated area: 3,423 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade;
  • Replacement of facade openings;
  • Installation of dynamic thermostatic radiator valves;
  • Improvement of the central heating system;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;

Total investments (BAM with VAT): 455,782.28
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 49,213
Total energy savings (thermal and electrical): 363,661.00 kWh/year
CO2 emissions: 100 tCO2 /year
Works completed: 11/2016

Public Institution Elementary School Hamdija Kresevljakovic, Kakanj

PUBLIC INSTITUTION ELEMENTARY SCHOOL HAMDIJA KRESEVLJAKOVIC, KAKANJ

Address: Šehida 2, Kakanj

Heated area: 3,120 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade and ceiling of the pitched roof;
  • Replacement of facade openings;
  • Improvement of the central heating system;
  • Installation of dynamic thermostatic radiator valves;
  • Partial replacement of lighting fixtures with more energy efficient ones;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment

Total investments (BAM with VAT): 332,627.59
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 49,894
Total energy savings (thermal and electrical): 368,745.00 kWh/year
CO2 emissions: 100 tCO2 /year
Works completed: 11/2016

Tešanj General Hospital

TEŠANJ GENERAL HOSPITAL

Address: Braće Pobrić, Tešanj

Heated area: 5,844 m2


Energy efficiency measures:

 

  • Thermal insulation of the facade;
  • Replacement of facade openings;
  • Thermal insulation of the attic and roof;
  • Installation of new pellet boilers;
  • Reconstruction of the roof;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;

Total investments (BAM with VAT): 718,293.76
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 161,082
Total energy savings (thermal and electrical): 686,930.00 kWh/year
CO2 emissions: 130 tCO2 /year
Works completed: 11/2016

Combined Secondary School, Žepče

COMBINED SECONDARY SCHOOL, ZEPCE

Address: Zagrebačka 2, Žepče

Heated area: 1,860 m2


Energy efficiency measures:

 

  • Thermal insulation of facade and the ceiling of the sloping roof;
  • Partial replacement of facade openings;
  • Installation of dynamic thermostatic radiator valves;
  • Replacement of lighting fixtures with more energy efficient ones;
  • Installation of equipment for measuring energy consumption;
  • Installation of temperature and humidity monitoring equipment;
  • Improvement of the central heating system;

Total investments (BAM with VAT): 170,792.39
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 22,152
Total energy savings (thermal and electrical): 158,650.00 kWh/year
CO2 emissions: 28 tCO2 /year
Works completed: 11/2016