ELEMENTARY SCHOOL SAFVET-BEG BAŠAGIĆ BREZA
Address: Breza
Heated area: 2,260 m2
Energy efficiency measures:
- Thermal insulation of facade walls;
- Thermal insulation of the ceiling;
- Replacement of existing joinery/metalwork;
- Installation of equipment for measuring energy consumption;
- Installation of temperature and humidity monitoring equipment;
Total investments (BAM with VAT): 496,273.14
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 19,880.13
Total energy savings (thermal and electrical): 71.729 kWh/year
CO2 emissions: 20 tCO2 /year
Start of works: 5/10/2021
Works completed/Date of technical acceptance: 2/8/2022