About project
PRIMARY SCHOOL “MIROSLAV KRLEŽA”
Address: Travnička cesta, Zenica
Heated area: 3,443 m2
Energy efficiency measures:
- Thermal insulation of facade walls;
- Installation of thermostatic valves;
- Partial replacement of lighting fixtures;
Total investments (BAM with VAT): 447,541.72
Total energy savings (thermal and electrical): 336,851kWh/year
CO2 emissions: 95 tCO2/year
Start of works: 20/10/2022
Works completed/Date of technical acceptance: 24/03/2023