About project
PUBLIC INSTITUTION ELEMENTARY SCHOOL KULIN BAN TEŠANJKA
Address: Trg žrtava osmog oktobra, Tešanjka
Heated area: 1,633.50 m2
Energy efficiency measures:
- Thermal insulation of facade walls;
- Thermal insulation of the ceiling;
- Replacement of existing joinery/metalwork;
- Replacement of asbestos cover;
- Installation of equipment for measuring energy consumption;
- Installation of temperature and humidity monitoring equipment;
Total investments (BAM with VAT): 316,997.60
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 21,550
Total energy savings (thermal and electrical): 381.050 kWh/year
CO2 emissions: 0 tCO2 /year
Start of works: 21/09/2021
Works completed/Date of technical acceptance: 20/04/2022