Health Centre Čitluk

HEALTH CENTRE ČITLUK

Stjepana Radića 3, Čitluk

Heated area: 2,004.6 m2


Energy efficiency measures:

 

  • Replacement of facade openings
  • Thermal insulation of walls

Total investments (BAM with VAT): 252,696.58 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 41,648.00
Total energy savings (thermal and electrical):  302.007 kWh/year
CO2 emissions: 33 tCO2 /year
Works completed: 10/2020

Public Institution Cultural Centre for culture “People’s Univerzity of Konjic”

PUBLIC INSTITUTION CULTURAL CENTRE PEOPLE’S UNIVERSITY OF KONJIC

Varda bb, Konjic

Heated area: 3,578 m2


Energy efficiency measures:

 
  • Thermal insulation of external walls;
  • Thermal insulation of the ceiling;
  • Replacement of facade openings;
  • Replacement of lighting fixtures with more energy efficient ones;

Total investments (BAM with VAT): 669,088.01 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 92,985.00
Total energy savings (thermal and electrical): 502,729 kWh/year
CO2 emissions: 312 tCO2 /year
Works completed: 10/2020

Public Institution Secondary School Prozor-Rama

PUBLIC INSTITUTION SECONDARY SCHOOL PROZOR-RAMA

Kralja Tomislava bb, Prozor-Rama

Heated area: 1,905 m2

Energy efficiency measures:

  • Thermal insulation of external walls;
  • Renovation of the roof structure, replacement of the roof covering and thermal insulation of the ceiling above the heated space;
  • Improvement of the heating system;
  • Partial replacement of facade openings;

Total investments (BAM with VAT): 200.739.28
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 38,038.00
Total energy savings (thermal and electrical): 101,855.00 kWh/year
CO2 emissions: 57 tCO2 /year
Works completed: 10/2020

Ambulance Building Čapljina

Ambulance Building Čapljina

Fra Didaka Buntića bb, Čapljina

Area: 2.471,5 m2

Energy efficiency measures:

  • Thermal insulation of external walls
  • Replacement of the external openings
  • Improvement of ceilings above heated area

Estimated investment for energy efficiency measures: 239.836,17 BAM

Estimated savings in energy costs after the implementation of schemes (BAM with VAT): 69.510,00

Expected annual CO2 emission reduction of 188 tCO2/yr
Expected annual energy savings: 302.077 kWh/yr

Public Institution Secondary School for Environment and wood design

PUBLIC INSTITUTION SECONDARY SCHOOL FOR ENVIRONMENT AND WOOD DESIGN

Address: Vilsonovo šetalište 11, Sarajevo

Heated area: 2,639.39 m2


Energy efficiency measures:

 
  • Thermal insulation of external walls;
  • Rehabilitation of the existing roof of the school building and sports hall, with the installation of thermal insulation;
  • Opening replacement;
  • Replacement of equipment and improvement of the space heating system;
  • Replacement of lighting fixtures with more energy efficient ones

Total investments (BAM with VAT): 626,860.93
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 56,302.74
Total energy savings (thermal and electrical): 510.597,00 kWh/year
CO2 emissions: 136 tCO2 /year
Works completed: 09/2020

Public Institution Elementary school Drvar

PUBLIC INSTITUTION ELEMENTARY SCHOOL DRVAR

Pionirska bb, Drvar

Heated area: 5,893 m2


Energy efficiency measures:

 

  • Renovation of the roof structure of the gymnasium and locker room area, and installation of a roof covering made of thermal panels;
  • Thermal insulation of the ceiling above the heated area of the old and new school;
  • Replacement of the facade openings of the gymnasium, locker room area and boiler room;
  • Installation of dynamic thermostatic valves;
  • Improvement of the heating system;

Total investments (BAM with VAT): 180,067.96 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 7,640.00
Total energy savings (thermal and electrical): 127,215 kWh/year
CO2 emissions: 3 tCO2 /year
Works completed: 09/2020

Secondary Transportation School/ Secondary School of Mechanical Engineering and Transportation

SECONDARY TRANSPORTATION SCHOOL/SECONDARY SCHOOL OF MECHANICAL ENGINEERING AND TRANSPORTATION

Address: Dr. Mile Budaka br.26, Mostar

Heated area: 2,900 m2


Energy efficiency measures:

 

  • Replacement of facade openings;
  • Thermal insulation of external walls;
  • Thermal insulation of the ceiling above the heated space;
  • Installation of the new pellet boiler;
  • Replacement of energy source;
  • Partial replacement of lighting fixtures with more energy efficient ones;

Total investments (BAM with VAT): 403,202.32 
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 60,386
Total energy savings (thermal and electrical): 284,898 kWh/year
CO2 emissions: 121 tCO2 /year
Works completed: 10/2020