About project
PUBLIC INSTITUTION ELEMENTARY SCHOOL ANTUN BRANKO ŠIMIĆ
Address: Kraljice Katarine 38, 88 000 Mostar
Heated area: 3,585 m2
Energy efficiency measures:
- Thermal insulation of the facade;
- Thermal insulation of the ceiling above the unheated basement;
- Thermal insulation of the envelope of the flat roof with additional thermal insulation;
- Thermal insulation of the ceiling with additional thermal insulation;
- Renovation of the roof structure and replacement of the roof covering;
- Replacement of facade openings;
- Improvement of the electricity consumption system;
- Improvement of the central heating system;
Total investments (BAM with VAT): 792,865.39
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 57,607
Total energy savings (thermal and electrical): 603,825.00 kWh/year
CO2 emissions: 0 tCO2 /year
(before the renovation, biomass was also used as the primary energy source)
Works completed: 5/2019