Navigation

Ivan Fra Frane Jukića Elementary School

About project

IVAN FRA FRANE JUKIĆA ELEMENTARY SCHOOL

Address: Sivša bb, Usora

Heated area: 488 m2


Energy efficiency measures:

 
  • Thermal insulation of the facade;
  • Thermal insulation of the ceiling towards the attic;
  • Replacement of lighting fixtures with more energy efficient ones;
  • Installation of the new pellet boiler;
  • Installation of equipment for measuring energy consumption;
  • Installation of equipment for monitoring temperature and humidity;

Total investments (BAM with VAT): 86,483.84
Estimated savings on energy costs after the realization of the sub-project, on an annual basis – calculated (BAM): 4,899
Total energy savings (thermal and electrical): 14,517.00 kWh/year
CO2 emissions: 21 tCO2 /year
Works completed: 04/2018

Pictures before works
Pictures during works
Pictures after works

KOMENTARI

PITANJA

Select a topic that best fits your question.
Question in one sentence
An account for you will be created and a confirmation link will be sent to you with the password.

Nema više pitanja po Vašoj pretrazi ili nemate dozvole za čitanje istih.

Question and answer is powered by anspress.net

Nema više pitanja po Vašoj pretrazi ili nemate dozvole za čitanje istih.

Question and answer is powered by anspress.net
Uspješno poslano