About project
COUNTY / CANTONAL COURT IN MOSTAR
Address: Ante Starčevića 22, Mostar
Heated area: 2,005 m2
Energy efficiency measures:
- Thermal insulation of facade walls, ceiling and roof;
- Replacement of existing carpentry;
- Improving the central heating system;
- Partial replacement of lighting fixtures;
Total investments (BAM with VAT): 912,155.51
Total energy savings (thermal and electrical): 602.093 kWh/year
CO2 emissions: 2,1 tCO2/year
Start of works: 10/11/2022
Works completed/Date of technical acceptance: 10/03/2023